Investigate IPD Factors' Effect on Value Engineering for the Communication Sector in Iraq

Main Article Content

Prween S. Majeed
Mervit R. ALTaie

Abstract

Integrated project delivery is collaboratively applying the skills and knowledge of all participants to optimize the project's results, increase owner value, decrease waste, and maximize efficiency during the design, fabrication, and construction processes. This study aims to determine IPD criteria positively impacting value engineering. To do this, the study has considered 9 main criteria according to PMP classification that already covers all project phases and 183 sub-criteria obtained from theoretical study and expert interviews (fieldwork). In this study, the SPSS (V26) program was used to analyze the main criteria and sub-criteria priorities from top to bottom according to their values of the Relative Importance Index. The results of this study have clarified the) Project stockholders Management ( as the most significant main criteria with RII (74%) and (Stakeholders, work team, customers, suppliers, and project managers' support improve the probability of project implementation on the ground) as the most significant sub-criteria with (RII) (91%)

Article Details

How to Cite
“Investigate IPD Factors’ Effect on Value Engineering for the Communication Sector in Iraq” (2024) Journal of Engineering, 30(01), pp. 90–105. doi:10.31026/j.eng.2024.01.06.
Section
Articles
Author Biography

Mervit R. ALTaie, Baghdad university

Civil engineering/project management 

How to Cite

“Investigate IPD Factors’ Effect on Value Engineering for the Communication Sector in Iraq” (2024) Journal of Engineering, 30(01), pp. 90–105. doi:10.31026/j.eng.2024.01.06.

Publication Dates

References

Abbas, N.N., and Burhan, A.M., 2023. Evaluation of the current status of the cost control processes in Iraqi construction projects. Journal of Engineering, 29(1), pp. 128-144. Doi:10.31026/j.eng.2023.01.08.

Abbas, N.N., and Burhan, A.M., 2022. Investigating the causes of poor cost control in Iraqi construction projects. Engineering, Technology & Applied Science Research, 12(1), pp. 8075-8079. Doi:10.48084/etasr.4661.

Atabay, S., and Galipogullari, N., 2013. Application of value engineering in construction projects. 10th International Congress on Advances in Civil Engineering, 17-19 October 2012 Middle East Technical University, Ankara, Turkey, pp. 78-87.

Brahmi Bani, F., Kitouni, I., and Sassi Boudemagh, S., 2022. Integrated project delivery and building information modeling assessment for sustainable renovation of heritage buildings, Doctoral dissertation, University of Constantine 3 Salah Boubnider, Faculty of Architecture and Urban Design.

de Carvalho, M., 2016. Mean, what do you Mean?. The American Statistician, 70(3), pp. 270-274. Doi:10.1080/00031305.2016.1148632

Doos, Q.M., Al-Saadwi, K.R., and Ibraheem, H.K., 2016. Evaluation of maintenance management in Iraqi governmental buildings. Journal of Engineering, 22(9), pp. 55-71. Doi:10.31026/j.eng.2016.09.04.

El Asmar, M., and Hanna, A.S., 2012. Comparative analysis of integrated project delivery (IPD) cost and quality performance. In Proceedings of the CIB W78 2012: 29th International Conference –Beirut, Lebanon, 17-19 October, Vol. 78, P. 2012.

Elsayed, E.A., 2012. Overview of reliability testing. IEEE Transactions on Reliability, 61(2), pp. 282-291. Doi: 10.1109/TR.2012.2194190

Field, A., 2013. Discovering statistics using IBM SPSS statistics. The Second Edition.

Fischer, M., Ashcraft, H.W., Reed, D., and Khanzode, A., 2017. Integrating project delivery. John Wiley & Sons.

Giachino, J., Cecil, M., Husselbee, B., and Matthews, C., 2016, February. Alternative project delivery: Construction management at risk, design-build, and public-private partnerships. In Utility Management Conference 2016. Water Environment Federation.

Gorter, R., Fox, J.P., and Twisk, J.W., 2015. Why item response theory should be used for longitudinal questionnaire data analysis in medical research. BMC Medical Research Methodology, 15(1), pp. 1-12. Doi:10.1186/s12874-015-0050-x

Guide, A.I.A., 2007. Integrated project delivery: A guide. American Institute of Architects, California.

Hall, D.M., and Scott, W.R., 2019. Early stages in the institutionalization of integrated project delivery. Project Management Journal, 50(2), pp. 128-143. Doi:10.1177/8756972818819.

Ibengwe, L.J., and Onyango, P.O., 2023. Capturing the invisible: Methodological approach in understanding informal cross border fish trade. Marine Policy, 149, P. 105482. Doi:10.1016/j.marpol.2023.105482

Kahvandi, Z., Saghatforoush, E., Alinezhad, M., and Noghli, F., 2017. Integrated Project Delivery (IPD) research trends. Journal of Engineering, Project, and Production Management, 7(2), P. 99. Doi:10.32738/JEPPM.201707.0006

Kassem, M.A., Khoiry, M.A., and Hamzah, N., 2020. Using relative importance index method for developing risk map in oil and gas construction projects. Jurnal Kejuruteraan, 32(3), pp. 441-453. Doi:10.17576/jkukm-2020-32(3)-09.

Lampert, M., 2010. Learning teaching in, from, and for practice: What do we mean?. Journal of teacher education, 61(1-2), pp. 21-34. Doi:10.1177/0022487109347321

Li, H., Qin, K., and Li, P., 2015. Selection of project delivery approach with unascertained model. Kybernetes, 44(2), pp. 238-252. Doi:10.1108/K-01-2014-0012

Lichtig, W.A., 2010. The integrated agreement for lean project delivery. Improving healthcare through built environment infrastructure, pp. 85-101. Doi:10.1002/9781444319675.ch6.

Majeed, R.A., and Breesam, H.K., 2021. The criteria for selecting the landfill sites in Baghdad governorate. IOP Conference Series: Materials Science and Engineering (Vol. 1090, No. 1, p. 012013), 1st International Conference on Engineering Science and Technology (ICEST 2020) 23rd-24th Dec. 2020, Samawah, Iraq. Doi:10.1088/1757-899X/1090/1/012013.

Miles, L.D., 2015. Techniques of value analysis and engineering. Miles Value Foundation.

Mohammad, S.R., and Mahdi, A.M., 2014. The risks causing claims and the procedures that can be followed in order to avoid them or reduce them to a minimum. Journal of Engineering, 20(10), pp. 1-18. (In Arabic) Doi:10.31026/j.eng.2014.10.10

Nigjeh, M.J., and Amani, N., 2022. Evaluation of influential value engineering factors on the function of interchanges: case studies in Iran. Journal of Engineering and Applied Science, 69(1), pp.1-15. doi: 10.1186/s44147-022-00100-9.

Noori, H., and Rasheed, S., 2023. Procurement Management of Power Plants Construction Projects in Iraq. Journal of Engineering, 29(2), pp. 37-58. Doi:10.31026/j.eng.2023.02.03.

Pershing, J.L., 2006. A commentary on quantitative and qualitative methods. Handbook of human performance technology, p.745.

Pishdad-Bozorgi, P., 2017. Case studies on the role of integrated project delivery (IPD) approach on the establishment and promotion of trust. International Journal of Construction Education and Research, 13(2), pp. 102-124. Doi:10.1080/15578771.2016.1226213.

Roberts, P., and Priest, H., 2006. Reliability and validity in research. Nursing Standard, 20(44), pp.41-46.

Salkind, N.J., 2010. Encyclopedia of research design (Vol. 1). sage.

Samarghandi, H., Mousavi, S., Taabayan, P., Mir Hashemi, A., and Willoughby, K., 2016. Studying the reasons for delay and cost overrun in construction projects: The Case of Iran. Journal of Construction in Developing Countries, 21(1), pp. 51-84. Doi:10.21315/jcdc2016.21.1.4

Siegel, S., and Castellan, N.J.Jr., 2008. Nonparametric statistics for the behavioral sciences, McGraw-Hill.

Taherdoost, H., 2016. Validity and reliability of the research instrument; how to test the validation of a questionnaire/survey in a research. How to test the validation of a questionnaire/survey in a research (August 10, 2016).

Teijlingen, E.V., and Hundley, V., 2002. The importance of pilot studies. Nursing standard, 16(40), pp. 33-36. Doi:10.7748/ns2002.06.16.40.33.c3214

Victorson, D., Murphy, K., Benedict, C., Horowitz, B., Maletich, C., Cordero, E., Salsman, J.M., Smith, K., and Sanford, S., 2020. A randomized pilot study of mindfulness‐based stress reduction in a young adult cancer sample: Feasibility, acceptability, and changes in patient reported outcomes. Psycho‐Oncology, 29(5), pp. 841-850. Doi:10.1002/pon.5355

Yihua, M., and Tuo, X., 2011. Research of 4M1E's effect on engineering quality based on structural equation model. Systems Engineering Procedia, 1, pp. 213-220. Doi:10.1016/j.sepro.2011.08.034

Yu, T., Shen, G.Q., and Shi, Q., 2017. Comparing the performance quality of design-bid-build and design-build delivery methods. Journal of Construction Engineering and Management, 143(4), P. 04016111. Doi:10.1061/(ASCE)CO.1943-7862.000126

Similar Articles

You may also start an advanced similarity search for this article.