Identifying Failure Factors in the Implementation of Residential Complex Projects in Iraq

Main Article Content

Meervat R. Altaie
Kennedy Onyelowe

Abstract

Residential complexes have witnessed a great demand in most countries worldwide, as they are one of the main infrastructure elements, in addition to achieving a developed urban landscape. However, complex residential projects in developing countries face various factors that could be improved in their implementation, especially in Iraq. Sixty-two experts in residential complex projects were interviewed and surveyed to verify these projects' failure factors,. Fifty-one factors were the main failure factors, divided into four main components (leadership, management system, external forces, and project resources). The Relatively Important Index (RII) is used to determine the relative importance factors and obtain the top twelve factors that cause the optimal failure factors, correspondingly: political interference (87.7%), change in governments (86.5%), partisan politics available (85.6%), Unclear strategic planning (84.3%), inadequate planning (84.3%), lack of materials and equipment (83.3%), the poor obligation for project leaders (82.6%), work suspension due to demonstrations (82.3%), lack of human capacity (81.8%), bureaucracy (81.7%), corruption (81.4%), and misalignment in culture or ethics (81.3%). The achieved RII readings were high for leadership (73.1%), followed by project resources (71.3%), management systems (70.5%), and external forces (69.9%). The study recommended addressing the problems of implementing complex residential projects and solving the crisis to start the state's economic growth phase according to new foundations and standards.


 

Article Details

Section

Articles

How to Cite

“Identifying Failure Factors in the Implementation of Residential Complex Projects in Iraq ” (2024) Journal of Engineering, 30(02), pp. 1–15. doi:10.31026/j.eng.2024.02.01.

References

Adagba, T., Shamsudeen, H., and Ati, J.O., 2023. An analysis of factors causing failures and abandonment of construction projects in Kaduna state, Nigeria. Global Journal of Business, Economics and Management: Current Issues, 13(3), pp. 215–230. Doi:10.18844/ gjbem.v13i3.8853

Adam, A.M., 2020. Sample size determination in survey research. Journal of Scientific Research and Reports, 26(5), pp. 90–97. Doi:10.9734/jsrr/2020/v26i530263

Adebisi, E.O., Ojo, S.O., and Alao, O.O., 2018. Assessment of factors influencing the failure and abandonment of multi-story building projects in Nigeria. International Journal of Building Pathology and Adaptation, 36(2), pp. 210-231. Doi:10.1108/IJBPA-10-2017-0048

Ahamed, Sk.A., Asadi, SS., 2017. Factors affecting the failure analysis of construction projects. International Journal of Civil Engineering and Technology (IJCIET), 8(1), pp. 390–396. http://iaeme.com/Home/issue/IJCIET?Volume=8andIssue=

Al-Ageeli, H.K., and Alzobaee, A.S.J.A., 2016. Critical success factors in construction projects (governmental projects as a case study). Journal of Engineering, 22(3), pp. 129–147. Doi:10.31026/j.eng.2016.03.09.

Alsaadi, A.A., and Ghasemlounia, R., 2021. Reasons for delaying the constriction projects in Iraq. International Journal of Engineering and Management Research, 11(1), pp. 129–133. Doi:10.31033/ijemr.11.1.18

Al-Sayyid, W.M., and Ali, S.H., 2021. Integrated project management strategies-residential investment case study. 2021. International Conference on Advance of Sustainable Engineering and its Application (ICASEA), pp. 200–205. Doi:10.1109/ ICASEA537 39.2021.9733070

Altaie, M., 2017. Optimal indicators to select the engineering consultancy office for higher education institutions in Iraq. Journal of Engineering, 23(9), pp. 45–63. Doi:10.31026/j.eng.2017.09.10.

Anatolevich, K.I., 2021. A study in the future of the transition to the federal budget of the federal Iraqi state. Proceedings of ‏The 3rd International Academic Conference on Management and Economics. pp. 78-99. Doi:10.33422/3rd.conferenceme.2021.06.248

Borku, W.T. and Yenialem, E., 2002. The cause of construction material wastage in building construction projects: a study in Wolaita zone, Southern Ethiopia. Journal of University of Shanghai for Science and Technology, 24(1), pp. 332-338. Doi:10.51201/jusst/22/0147

Çavdur, F., Sebatli, A., Kose-Kucuk, M., and Rodoplu, C., 2019. A two-phase binary-goal programming-based approach for optimal project-team formation. Journal of the Operational Research Society, 70(4), pp. 689 - 706. Doi:10.1080/01605682.2018.1457480

Damoah, I.S., Tingbani, I., Kumi, D.K., Akwei, C.C., and Amoako, I.O., 2019. Factors influencing school building construction projects abandonment. International Journal of Construction Management, 22(6), pp. 961-976. Doi:10.1080/15623599.2019.1675025

Damoah, I.S., and Kumi, D.K. , 2018. Causes of government construction projects failure in an emerging economy: Evidence from Ghana. International Journal of Managing Projects in Business, 11(3), pp. 558-582. Doi:10.1108/IJMPB-04-2017-0042

Enshassi, M.A., Hallaq, K.A., and Tayeh, B.A., 2019. Failure factors facing organizations in post-disaster housing reconstruction projects in Gaza strip. Civil Engineering Research Journal, 8(5), pp. 144- 152. Doi:10.19080/CERJ.2019.08.555750

Frimpong, Y.O., Oluwoye, J.O., and Crawford, L., 2003. Causes of delay and cost overruns in construction of groundwater projects in developing countries; Ghana as a case study. International Journal of Project Management, 21(5), pp. 321–326. Doi:10.1016/S0263-7863 (02) 000 55-8

Gad, N.A., Abdel-Monem, M., El-Dash, K., and Abdel-Hamid, M., 2022. Modeling financial risk contributes to construction projects; a case study of expansion food industries. HBRC Journal, 18(1), pp. 85 - 106. Doi:10.1080/16874048.2022.2086779

Homenko, O., Petrenko, Н., Ryzhakova, G., Petrukha, N., Chupryna, Y., Malykhina, O., and Kushnir, O., 2022. Modern tools and software products for the administration of construction organizations in the conditions of transformation of operational management systems. Management of Development of Complex Systems, 52(2), pp. 113-125. Doi:10.32347/ 2412- 9933.2022.52.113-125

Hwang, B., and Ng, W.J., 2013. Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), pp. 272-284. Doi:10.1016/j.ijproman.2012.05.004

Khoso, A.R., Khan, J.S., Faiz, R.U., and Akhund, M.A., 2019. Assessment of Change Orders Attributes in Preconstruction and Construction Phase. Civil Engineering Journal, 5(3), pp. 616- 623. Doi:10.28991/cej-2019-03091273

Li, J., Shen, Q. and Gao, W., 2022. Characterization of Group Behavior of Corruption in Construction Projects Based on Contagion Mechanism. Computational Intelligence and Neuroscience, 2022(1), pp. 1-16. Doi:10.1155/2022/8456197

Marwa, M., and Altaie, M. R., 2022. Use the Risk Score Method to Identify the Qualitative Risk Analysis Criteria in the Tendering Phase of Construction Projects. Journal of Engineering, 28(7), pp. 31–42. Doi:10.31026/j.eng.2022.07.03.

Mohammed, S.R., Naji, H.I., and Ali, R.H., 2019. Impact of the Feasibility Study on the Construction Projects. IOP Conference Series: Materials Science and Engineering, 518(2). pp. 1-99, https://doi.org /10.1088/1757-899X/518/2/022074

MOP Ministry of Planning, Iraq, 2019. The future we want, Iraq vision for Sustainable Development in 2030, 2019, andp.unescwa.org/sites/default/files/2021-05/The future we want-Iraq vision for Sustainable Development 2030.pdf

Muhsen, H.K., and Rezouki, S. E., 2022. The Causes Influencing the Occurrence of Variation Orders in the Construction of Buildings, Journal of Engineering, 28(8), pp. 34–53. Doi:10.31026/ j.eng.2022.08.03.

Nguyen, V.T., Do, S.T., Vo, N.M., Nguyen, T.A., and Pham, S.V., 2020. An analysis of construction failure factors to stakeholder coordinating performance in the finishing phase of high-rise building projects. Advances in Civil Engineering. P. 6633958, Doi:10.1155/2020/6633958

Obead, K.R., and Wali, M.R., 2020. Developing Systems Engineering for Sustainable Infrastructure Projects. IOP Conference Series: Materials Science and Engineering. 901(1), pp. 01–06. Doi:10.1088/1757-899X/901/1/012026

Ogunde, A.O., Eseohe, A., Opeyemi, J.A., Ebenezer, B.O., Amusan, L., and Ogunde, A., 2017. Project management: a panacea to improving the performance of construction projects in Ogun state, Nigeria. International Journal of Civil Engineering and Technology (IJCIET), 8(9), pp. 1234-1242.

Olugboyega, O., and Windapo, A.O., 2021. Investigating the strategic planning of bim adoption on construction projects in a developing country. Journal of Construction in Developing Countries, 27(2), pp. 183–204. Doi:10.21315/jcdc-02-21-0031

Osuizugbo, I.C., 2019. Project failure factors affecting building project success in Nigeria: design and construction phase. 16(10), pp. 01-11. Doi:10.9790/1684-1601050111

Shahbaz, M.S., Rasi, R.Z.R. and Ahmad, M.F.B., 2019. A novel classification of supply chain risks: Scale development and validation. Journal of Industrial Engineering and Management (JIEM), 12(1), pp.201-218. Doi:10.3926/jiem.2792

Shaikh, F.A., 2020. Financial Mismanagement: A leading cause of time and cost overrun in mega construction projects in Pakistan. Engineering, Technology and Applied Science Research, 10(1), pp. 5247–5250. Doi:10.48084/etasr.3271

Shehu, Z., Endut, I.R., Akintoye, A., and Holt, G.D., 2014. Cost overrun in the Malaysian construction industry projects: A deeper insight. International Journal of Project Management, 32 (8), pp. 1471–1480. Doi:10.1016/j.ijproman.2014.04.004

Sulieman, H.A., and Alfaraidy, F.A., 2019. Influences of project management capabilities on the organizational performance of the Saudi construction industry. Engineering, Technology, and Applied Science Research, 9(3), pp. 4144-4147. Doi:10.48084/etasr.2740

Tsao, Y.C., and Hsueh, S., 2022. Can the country's perception of corruption change? evidence of corruption perception index. Public Integrity, 25(4), pp. 415-427. Doi:10.1080/ 10999922.2022.2054571

Waheeb, R., 2023. Identification of delay causes in construction projects and emergency, reconstruction- Iraq as a case study. PhD in Civil Engineering, Norwegian University of Science and Technology Faculty of Engineering, Doi:10.2139/ ssrn.4449802

Zhang, B. and Li, Y., 2022. A User Profile of Tendering and Bidding Corruption in the Construction Industry Based on SOM Clustering: A Case Study of China. Buildings, 12(12), p.2103. Doi:10.3390/buildings12122103.

Zilfianah, K., Ismiyah, E., and Rizqi, A.W., 2022. Quality Control Analysis on Steel Construction Projects Using the Method Statistical Quality Control and Failure Mode and Effects Analysis. Journal of Mechanical, Electrical and Industrial Engineering. 5(1), pp. 13-32. Doi:10.46574/motivectio n.v5i1.174

Similar Articles

You may also start an advanced similarity search for this article.