Use Risk Score Method to Identify the Qualitative Risk Analysis Criteria in Tendering Phase in Construction Projects

محتوى المقالة الرئيسي

Marwa M
Meervat Razzaq Altaie

الملخص

The purpose of this article was to identify and assess the importance of risk factors in the tendering phase of construction projects. The construction project cannot succeed without the identification and categorization of these risk elements. In this article, a questionnaire for likelihood and impact was designed and distributed to a panel of specialists to analyze risk factors. The risk matrix was also used to research, explore, and identify the risks that influence the tendering phase of construction projects. The probability and impact values assigned to risk are used to calculate the risk's score. A risk matrix is created by combining probability and impact criteria. To determine the main risk elements for the tender phase of a construction project, this study constructed the matrix of probability and impact variables and put the periods based on the risk score. Finally, this study identified a fourth main risk group and twenty-two sub-risk factors that are appropriate for the tendering phase of construction projects in Iraq

تفاصيل المقالة

كيفية الاقتباس
"Use Risk Score Method to Identify the Qualitative Risk Analysis Criteria in Tendering Phase in Construction Projects" (2022) مجلة الهندسة, 28(7), ص 31–42. doi:10.31026/j.eng.2022.07.03.
القسم
Articles

كيفية الاقتباس

"Use Risk Score Method to Identify the Qualitative Risk Analysis Criteria in Tendering Phase in Construction Projects" (2022) مجلة الهندسة, 28(7), ص 31–42. doi:10.31026/j.eng.2022.07.03.

تواريخ المنشور

المراجع

• Duijm, N. J., 2015. Recommendations on the use and design of risk matrices, Safety Science, 76 (13), 21-31.‏

• Radu, L.D., 2009. Qualitative, semi-quantitative and quantitative methods for risk assessment, Case of the financial audit: Scientific Annals of the Alexandru Ioan Cuzaî University of Iasi: Economic Sciences Series, 9 (3), 643-657.

• Rowe and Right, 2001. Expert Opinions in Forecasting. Role of the Delphi Technique, In: Armstrong (Ed.): Principles of Forecasting: Kluwer Academic Publishers.

• Jardine, S., 2007. Managing risk in construction projects–how to achieve a successful outcome. PWC.

• Ali, C. et al., 2020. Improving the question formulation in Risk Score by Delphi‐like surveys: Analysis of the effects of abstract language and amount of information on response behavior. In: Futures & Foresight Science. e56, doi:10.1002/ffo2.56.

• Mauksch et al., 2020. Who is an expert for foresight? A review of identification methods. In: Technological Forecasting and Social Change.154(5),11-20.

• Ekung, S., Lashinde, A., and Adu, E., 2021. Critical Risks to Construction Cost Estimation. Journal of Engineering. Project & Production Management, 11(1),56-66

• Akintoye A.S. and MacLeod MJMJ., 1997. Risk analysis and management in construction, Int. J. Proj. Manag., 15(1), 31–38.

• Othmaan, O., Saaed, 1998. Predicting the Future. (Albany, NY: State University of New York Press.

• Farinloye, O. O., Salako, O. A., and Mafimidiwo, B. A., 2009. Construction professional's perception of risk impact on the cost of building projects in Nigeria construction industry. Proc., RICS COBRA, RICS, London, 70 (7), 227–243.

• Hosny, H. E., Ibrahim, A. H., and Elmalt, A. E., 2019. Factors affecting quality of tender documents. Al-Azhar University Civil Engineering Research Magazine (CERM), 41(1), 346-355.‏

• Odusami, K. T., and Onukwube, H. N., 2008. Factors affecting the accuracy of pre-tender cost estimate in Nigeria.” RICS COBRA, Royal Institution of Chartered Surveyors, Dublin Institute of Technology, Dublin, Ireland, 1–10

• Monetti, E., Rosa, S. A., and Rocha, R. M., 2006. The practice of project risk management in government projects: A case study in Sao Paulo City. Construction in developing economics: New issues and challenges, 18-20.

• Mohammed, Aksana Jihad., 2016. A study for Significant Risks and Their effects on Construction Projects in Erbil city. Journal of Engineering and Sustainable Development, 20(4).

• Kissi, E., Adjei-Kumi, T., Badu, E., and Boateng, E. B., 2017. Factors affecting tender price in the Ghanaian construction industry. Journal of Financial Management of Property and Construction.

• Mahamid, I., 2018.Critical determinants of public construction tendering costs. International Journal of Architecture, Engineering and Construction, 7(1), 34-42.‏

• Omran, A., and Hooi, L. B., 2018. Determining the critical factors in ensuring the accuracy of cost estimate in obtaining a tender, Acta Technical Corviniensis-Bulletin of Engineering.

• Bakr, G. A., 2019. Identifying crucial factors affecting accuracy of cost estimates at the tendering phase of public construction projects in Jordan. International Journal of Civil Engineering and Technology, 10(1), 1335-1348.

• Town C., Mohamed L., Hesham O. and Middlands W., 2016. Risk management for multinational collaborations: application on the case study of grand Egyptian museum.

• Ghahramanzadeh M., 2013. Managing Risk of Construction Projects: A case study of Iran.

• Baloi D., and Price ADF.,2003. Modeling global risk factors affecting construction cost performance. Int. J. Proj. Manag., 21, 261–269

• Zou PXW., Zhang G., and Wang J., 2007. Understanding the key risks in construction projects in China. Int. J. Proj. Manag., 25(6), 601–614.

• Elhag, T.M.S., Boussabaine, A.H., and Ballal, T.M.A., 2005. Critical determinants of construction tendering costs: Quantity surveyors standpoint. International Journal of Project Management, 23(7): 538–545.

• Dikmen I., Birgonul M.T., and Han S., 2007. Using fuzzy risk assessment to rate cost overrun risk in international construction projects. Int. J. Proj. Manag., 25(5), 494–505.

• TAH J.H.M., and Carr V., 2001. Towards a framework for project risk knowledge management in the construction supply chain, Adv. Eng. Softw., 32 (10–11), 835–846.

• Roger F.,1993. Risk Management and Construction-Blackwell Scientific.

• Wang, S. Q., Dulaimi, M. F., and Aguila, M. Y., 2004. Risk management framework for construction projects in developing countries. Constr. Manag. Econ., 22 (3), 237–252.

• Ghosh S., and Jintanapakanont J., 2004. Identifying and assessing the critical risk factors in an underground rail project in Thailand: A factor analysis approach. Int. J. Proj. Manag., 22(8), 633–643.

• Enshassi, A., Mohamed, S., and Abdel-Hadi, M., 2013. Factors affecting the accuracy of pre-tender cost estimates in the Gaza Strip. Journal of Construction in Developing Countries, 18(1).

• Issa U.H., Farag M.A., Abdelhafez L.M., and Ahmed S.A., 2015. A risk allocation model for construction projects in Yemen, 7(3), 78–89.

• Samson S., Reneke J.A. and Wiecek M.M.., 2009. A review of different perspectives on uncertainty and risk and an alternative modeling paradigm. Reliab. Eng. Syst. Saf, 94, (2) 558–567

• Smith N., Merna T., and Jobling P., 2006. Managing risk in construction projects.

• Cooper M.D.F., Stephen G., Geoffrey Raymond, and Phil Walker Gopal, 2005. Project Risk Management Guidelines.

• Suherman, S. A., 2010. Tips Jitu Menang Tender Menjadi Pemenang Sebelum Tender Dimulai. Cetakan. Yogyakarta: Media Pressindo.

• GP House., 2013. Identifying assessing and evaluating risks affecting the educational construction projects in Saudi Arabia. Int. J. Proj. Manag.,25(6), 105–116.

• Augustine I.E., Ajayi J.R., Ade B.A., and Edwin A.A., 2012. Assessment of risk management practices in the Nigerian construction industry: Toward establishing risk management index, Int.

المؤلفات المشابهة

يمكنك أيضاً إبدأ بحثاً متقدماً عن المشابهات لهذا المؤلَّف.