Procurement Management of Power Plants Construction Projects in Iraq

Main Article Content

Hamza Noori
Sawsan Rasheed

Abstract

The government of Iraq states that despite the massive amounts invested in the power generating sector, the country has been plagued by power outages for more than three decades; One of the most common sources of the problem and significant impact on the waste of public funds in contractual processes. The Ministry of Planning issued the sectorial
specialized standard bidding documents (SSBD) of Design, Supply, and Installation of the Electromechanical Works (DSIoEW), which is primarily designed to support the Ministry of Electricity (MoE) by developing economic projects to improve the contractual process that led to raisings Iraqi electricity generation field. The research evaluates the impact of
applying the SSBD-DSIoEW for governmental power generation plants and investigates the challenges and obstacles of SSBD-DSIoEW applications in Iraq by conducting preliminary interviews with procurement experts and distributing 120 questionnaires to MoE's contractual staff. The results show a lack of experience in applying the evaluation and qualification criteria under SSBD-DSIoEW, and inadequate bid evaluations, resulting in an ineffective procurement system. In the study's conclusion and based on the results, the authors developed a unified bids evaluation model. They structured it in a computerized application program to support bids' evaluation committees

Article Details

Section

Articles

How to Cite

“Procurement Management of Power Plants Construction Projects in Iraq” (2023) Journal of Engineering, 29(02), pp. 37–58. doi:10.31026/j.eng.2023.02.03.

References

Al-Ageeli, H. K., and Alzobaee, A. S. J. A., 2016. Critical Success Factors in Construction Projects (Governmental Projects as a Case Study), Journal of Engineering, 22(3), pp.129–147. Retrieved from https://joe.uobaghdad.edu.iq/index.php/main/article/view/249.

Altai, H. D. S., Abed, F. T., Lazim, M. H., and ALRikabi, H. T. S., 2022. Analysis of the problems of electricity in Iraq and recommendations of methods of overcoming them, Periodicals of Engineering and Natural Sciences (PEN), 10(1), pp.607-614.

Arditi, D., 2016. Impact of Bidding Environment on Change Orders, Proceedings of International Structural Engineering and Construction.

Ashkanani, S., and Franzoi, R., 2022. An overview on megaproject management systems, Management Matters, (ahead-of-print)

Delatte, J., 2017. Challenges of civil engineering megaprojects in North America, Proceedings of Institution of Civil Engineers Management, Procurement and Law, Vol. 170, pp. 1.

Eriksson, P.E., and Szentes, H., 2017. Managing the tensions between exploration and exploitation in large construction projects, Construction Innovation, 17 (4), pp. 492–510.

Erzaij, K.R., and Aljanabei, D.M., 2016. Performance Evaluation of the Investment Projects during the Implementation Phase (Najaf province as a case study), Journal of Engineering, 22, 8, Aug., pp. 54–74.

Flanagan, R., and Jewell, C., 2018. New code of estimating practice.61-166, DOI: 10.1680/JMAPL.17.00012.

Garrett, G. A., 2015. World class contracting (p. 448), Wolters Kluwer.‏

Hamza S.A., Rasheed S., Hussein A., 2022. Procurement challenges analysis of Iraqi construction projects, Journal of the Mechanical Behavior of Materials, 31 (1), pp.112-7.

Hassan S., 2020. Analysis The Implementation of Standard Bidding Documents and Their Impact On Contractors and contracting Entities.

Jackson, B. J., 2020. Construction management JumpStart: the best first step toward a career in construction management, John Wiley & Sons.‏

Joint Contracts Tribunal, 2011. Practice Note – Deciding on the Appropriate JCT Contract, Sweet & Maxwell Limited, London, UK.

Ministry of Planning. Directorate of General Government Contracts-Standard Bidding Documents. Available from: https://mop.gov.iq/office_ministry/view/

detailsid=19&sub_content=114&id_sub_content=0&sub2content=nothing

Ministry of Planning. Directorate of General Government Contracts-Regulation of Execution Governmental Contracts. Available from:https://mop.gov.iq/office_ministry/view/

detailsid=19&sub_content=111&id_sub_content=0&sub2content=nothing

Morris, P. W., and Pinto, J. K., (Eds.), 2010. The Wiley guide to project technology, supply chain, and procurement management, John Wiley & Sons.‏

Robinson, W. S., 2009. Ecological correlations and the behavior of individuals, International Journal of Epidemiology, 38(2), pp. 337-341

Taherdoost, H., 2019. What is the best response scale for survey and questionnaire design; review of different lengths of rating scale/attitude scale/Likert scale, Hamed Taherdoost, pp.1-10

World Bank., 2022. The World Bank in Iraq – Overview, Available at https://www.worldbank.org/en/country/iraq/overview#1

Similar Articles

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)