The Delay and Failure of Residential Investment Projects in Iraq: Review

Main Article Content

Aya A. Hasan
Abbas M. Burhan

Abstract

One of the challenges that arises frequently when carrying out residential investment projects is building delays. This study aims to fill this gap and add more to the body of knowledge about residential investment projects in Iraq. The research methodology was divided into two sections: one on previous studies, as mentioned in this research, and the other on techniques and tools for reducing residential project delays. The researcher concluded that there are several issues with residential projects, like inadequate project comprehension, outdated methods, untrained contractors, etc. This issue is not readily resolved and can have a detrimental effect on the project's outcome, including cost overruns, subpar work, a lack of safety, and schedule delays. In addition to other detrimental social effects, project delays may occur at some point during the construction process, and in certain cases, even when the project is completed. A construction project must be completed on schedule and within the projected budget. Approximately eighty-four pertinent articles over the past twenty-five years have been examined. This issue has a direct influence on people's lives and social welfare. Implementing residential project policies for new clients has sparked building projects and increased demand for residential buildings. However, a lot of residential projects were abandoned or never finished, which seriously concerned the government.

Article Details

Section

Articles

How to Cite

“The Delay and Failure of Residential Investment Projects in Iraq: Review” (2025) Journal of Engineering, 31(2), pp. 48–71. doi:10.31026/j.eng.2025.02.04.

References

Abd El‐Razek, M.E., Bassioni, H.A. and Mobarak, A.M., 2008. Causes of delay in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11), pp. 831‐841.

Abdul-Adheem, W.K. and Abdul-Lateef, M.G., 2020. Designing investment map and building geographical database for investment projects in Baghdad governorate. Al-Adab Journal, 134, pp. 311-328. https://doi.org/10.31973/aj.v0i134.1066

Abedi, M., 2011. Effects of construction delays on construction project objectives. The First Iranian Students Scientific Conference in Malaysia, pp. 1–8.

Adagba, T., Shamsudeen, H., and Ati, J.O., 2023. An analysis of factors causing failures and abandonment of construction projects in Kaduna state, Nigeria. Global Journal of Business, Economics and Management, 13(3), pp. 215–230. https://doi.org/10.18844/gjbem.v13i3.8853

Adebisi, E.O., Ojo, S.O., and Alao, O.O., 2018. Assessment of factors influencing the failure and abandonment of multi-story building projects in Nigeria. International Journal of Building Pathology and Adaptation, 36(2), pp. 210-231. https://doi.org/10.1108/IJBPA-10-2017-0048

Ahamed, Sk.A., Asadi, S.S., 2017. Factors affecting the failure analysis of construction projects. International Journal of Civil Engineering and Technology (IJCIET), 8(1), pp.390–396.

Aibinu, A.A. and Jagboro, G.O., 2002. The effects of construction delay on project delivery in Nigerian construction industry. International National Journals of Project Management, 20 (8), pp. 593-599. https://doi.org/10.1016/S0263-7863(02)00028-5

Aiyetan, A.O., Smallwood, J. and Shakantu, W., 2012. A linear regression modelling of the relationship between initial estimated and final achieved construction time in South Africa. Acta Structilia, 19(1), pp. 39– 56. https://doi.org/10.38140/as.v19i1.121

AL musawi, L. and Naimi, S.,2023. The management of construction projects in Iraq and the most important reasons for the delay. Journal about Logistics International Scientific, 10 (1), p.p. 61-70. https://doi.org/10.22306/al.v10i1.351

Al-Ageeli, H.K. and Alzobaee, A.S.J.A., 2016. Critical success factors in construction projects (Governmental projects as a case study). Journal of Engineering, 22(3), pp. 129-147. https://doi.org/10.31026/j.eng.2016.03.09

Al-Emad, N. and Nagapan, S., 2015. Identification of delay factors from Mecca's construction expert's perspective. International Journal of Sustainable Construction Engineering & Technology, 6 (2), pp.16-25.

AlGheth , A. and Sayuti, M. I., 2019. contributing factors to schedule delays in construction projects in the United Arab Emirates. International Journal of Engineering and Advanced Technology (IJEAT). 8(6S3), pp. 422-433. https://doi.org/10.35940/ijeat.F1076.0986S319

Al-Hammadi, S. and Nawab, M.S., 2016. Study of delay factors in construction projects. International Advanced Research Journal of Science Engineering and Technology, 3 (4), pp. 87-93.

Al-Moumani A., 2000. Construction delays: a quantitative analysis. International Journal of Project Management,18(4), pp. 51–59. https://doi.org/10.1016/S0263-7863(98)00060-X

Alsaadi, A.A., and Ghasemlounia, R., 2021. Reasons for delaying the constriction projects in Iraq. International Journal of Engineering and Management Research, 11(1), pp. 129–133. https://doi.org/10.31033/ijemr.11.1.18

Al-Sayyid, W.M., and Ali, S.H., 2021. Integrated project management strategies-residential investment case study. International Conference on Advance of Sustainable Engineering and its Application (ICASEA), pp. 200–205.

Altaie, M.R. and Borhan, A.M., 2018. Using neural network model to estimate the optimum time for repetitive construction projects in Iraq. Association of Arab Universities Journal of Engineering Sciences, 25 (5), pp. 100-114.

Altaie, M.R., and Onyelowe, K., 2024. Identifying failure factors in the implementation of residential complex projects in Iraq. Journal of Engineering, 30(2), pp. 1-15. https://doi.org/10.31026/j.eng.2024.02.01

Amoatey, C.T., Yaa A.A., Ebenezer, A. and Samuel, F., 2015. Analysing delay causes and effects in ghanaian state housing construction projects. International Journal of Managing Projects in Business, 8 (1), pp. 198–214. https://doi.org/10.1108/IJMPB-04-2014-0035

Bajjou, M.S. and Chafi, A. ,2018. Empirical study of schedule delay in Moroccan construction projects. International Journal of Construction Management, pp. 1-18. https://doi.org/10.1080/15623599.2018.1484859

Bekr, G.A., 2015. Identifying factors leading to cost overrun in construction projects in Jordan. Journal of Construction Engineering, Technology and Management. 5 (3), pp. 25–33.

Damoah, I.S., Akwei, C. and Mouzughi, Y., 2015. Causes of government project failure in developing countries – focus on Ghana: The value of pluralism in advancing management research, education, and practice. BAM2015 Conference Proceedings. 29th Annual BAM Conference, University of Portsmouth, Portsmouth, United Kingdom.

Damoah, I.S., Akwei, C.A., Amoako, I.O. and Botchie, D., 2018. Corruption as a source of government project failure in developing countries: evidence from Ghana. Project Management Journal, 49(3), pp. 17–33. https://doi.org/10.1177/8756972818770587

Desai, M. and Bhatt, R., 2013. Critical causes of delay in residential construction projects: Case study of Central Gujarat Region of India. International Journal of Engineering Trends and Technology (IJETT), 4 (4), pp. 762–768.

Dey, P. K., 2002. Project Risk Management: A combined analytical hierarchy process and decision tree approach. Cost Engineering, 44(3), pp. 13-26.

Dixit, S., Pandey, A.K., Mandal, S.N. and Bansal, S., 2017. A Study of enabling factors affecting construction productivity: Indian scenario. International Journal of Civil Engineering & Technology, 8(6), pp. 741–758.

Dlamini, M. and Cumberlege, R., 2021. the impact of cost overruns and delays in the construction business. The ASOCSA 14th Built Environment Conference, IOP Conference Series: Earth and Environmental Science, (pp. 1-10).

Doraisamy, S.V., Akasah, Z.A. and Khamis, A., 2016. A Model on the significant factors contributing towards the restoration of abandoned residential projects in Malaysia using AMOS-SEM. Australian Journal of Basic and Applied Sciences, 10(11), pp. 87–94.

Durdyev, S. and Ismail, S., 2016. On-site construction productivity in Malaysian infrastructure projects. Structural Survey, 34(4/5), pp. 446–462. https://doi.org/10.1108/SS-12-2015-0058

Durdyev, S., and Ismail, S., 2012. Role of the construction sector in the economic development of Turkmenistan. EEST Part A: Energy, Science and Research, 29(2), pp. 883–890.

Durdyev, S., Maksat, O. and Syuhaida, I., 2017. Causes of delay in residential construction projects in Cambodia. Cogent Engineering, 4, pp. 1–12. https://doi.org/10.1080/23311916.2017.1291117

Durdyev, S., Omarov, M., and Ismail, S., 2016. SWOT Analysis of the Cambodian construction industry within the ASEAN economic community. Proceedings of the 28th International Business Information Management Association Conference, Seville, pp. 2335- 2341.

Eja, K.M. and Ramegowda, M., 2020. Government project failure in developing countries: A review with particular reference to Nigeria. Global Journal of Social Sciences, 19, pp. 35–47. https://doi.org/10.4314/gjss.v19i1.4

Enshassi, A. and Ayyash, A., 2014. Factors affecting cost contingency in the construction industry – Contractors’ perspective. International Journal of Construction Management, 14(3), pp. 215–239. https://doi.org/10.1080/15623599.2014.922729

Erzaij, K.R., and Aljanabei, D.M., 2016. Performance evaluation of the investment projects during the implementation phase (Najaf province as a case study). Journal of Engineering, 22(8), pp. 54-74. https://doi.org/10.31026/j.eng.2016.08.04

Fadhil, G.A., and Burhan, A.M., 2022. Developing crisis management system for construction projects in Iraq. Journal of Engineering, 28(1), pp. 33-51. https://doi.org/10.31026/j.eng.2022.01.03

Faridi, A.S and El-Sayegh, S.M, 2006. Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), pp. 1167–1176. https://doi.org/10.1080/01446190600827033

Farooqui, R., Farrukh, A. and Rafeequi, A., 2008. Safety performance in construction industry of Pakistan. Proceedings of the 1st International Conference on Construction in the Developing Countries (ICCIDC-I), Karachi, Pakistan.

Fugar, F.D.K. and Agyakwah‐Baah, A.B., 2010. Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, 10(1-2), pp. 103‐116. https://doi.org/10.5130/AJCEB.v10i1-2.1592

Ghosh, S. and Jintanapakanont, J., 2004. Identifying and assessing the critical risk factors in an underground rail

project in Thailand: a factor analysis approach. Elsevier International Journal of Project Management, 22(8), pp. 633-643. https://doi.org/10.1016/j.ijproman.2004.05.004

Gunduz, M., Nielsen, Y. and Ozdemir, M., 2013. Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of Management in Engineering (ASCE), 29 (2), pp. 133 – 139. https://doi.org/10.1061/(ASCE)ME.1943-5479.000012

Haseeb, M., Xinhai-Lu, Bibi, A., Maloof-ud Dyian, and Rabbani, W., 2011. Problems of projects and effects of delays in the construction industry of Pakistan, Australian Journal of Business and Management Research, 1(5), pp. 41–50.

Hwang, B.G., Zhao, X. and Ng, S. Y., 2013. Identifying the critical factors affecting schedule performance of public housing projects. Habitat International, pp. 214–221. https://doi.org/10.1016/j.habitatint.2012.06.008

Kazaz, A., Ulubeyli, S., Tuncbilekli, N.A., 2012. Causes of delays in construction projects in Turkey. Journal of Civil Engineering and Management, 18(3), pp. 426‐435.

Khaleel, T.A. and Flayeh, M.A., 2020. Evaluation of risk factors affecting the implementation time for residential complex projects in Iraq. 3rd International Conference on Engineering Sciences IOP Conf. Series: Materials Science and Engineering 671 (2020) 012002, pp. 1-14.

Khamees, A.S. and Altaay, M.R., 2022. Optimizing methods of funding residential complexes projects. International Journal of Intelligent Systems and Applications in Engineering, 10(3), pp. 57-63

Khamees, A.S. and Altaay, M.R., 2022. Evaluating the efficiency of finance methods in residential complex projects in Iraq. Engineering, Technology & Applied Science Research, 12(1), pp. 8080-8084. https://doi.org/10.48084/etasr.4663

Kikwasi, G.J., 2012. Causes and effects of delays and disruptions in construction projects in Tanzania, Australasian Journal of Construction Economics and Building Conference Series, 1(2), pp. 52-59. https://doi.org/10.5130/ajceb-cs.v1i2.3166

Kim, S.Y., Nguyen, V.T. and Luu, V.T., 2015. Delay factors affecting the completion of the government construction projects in Vietnam. The 6th International Conference on Construction Engineering and Project Management (ICCEPM 2015) at Paradise Hotel, Busan, South Korea.

Komurlu, R. and Arditi, D., 2016. Delay management in building construction: a comparative study. Proceedings of International Structural Engineering and Construction, 3(1), pp. 431-436.

Koushki, P.A., Al-Rashid, K. and Kartam, N.,2005. Delays and cost increases in construction of private residential projects in Kuwait. Construction Management and Economics, 23(3), pp. 285–294. https://doi.org/10.1080/0144619042000326710

Krishnan, G.R. and Johny, M.A., 2016. Assessment of risk factors in construction project using PI method. International Research Journal of Engineering and Technology (IRJET). 3(9), pp. 767 -770.

Larsen, J.K., Shen, G.Q., Lindhard S.M. and Brunoe T.D., 2015. Factors affecting schedule delay, cost overrun, and quality level in public construction projects. Journal of Management in Engineering, 32(1), pp. 1-29. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129

Laryea, S. and Hughes, W., 2008. How contractors price risk in bids: theory and practice. Construction Management and Economics, 26(9), pp. 911–924. https://doi.org/10.1080/01446190802317718

Mahamid, I., 2011. Risk matrix for factors affecting time delay in road construction projects: owners’ perspective. Engineering, Construction and Architectural Management, 18(6), pp. 609-617. https://doi.org/10.1108/09699981111180917

Mahmood, S., Ahmed, S.M., Panthi, K. and Kureshi, N.I., 2014. Determining the cost of poor quality and its impact over productivity and profitability. Built Environment Project and Asset Management, 4 (3), pp. 296- 311.

Mahmoud, T.N. and Erzaij, K.R., 2023. Develop proactive system for risk management (DPSRM) for lagging investment project in Iraq. Journal of Engineering, 29 (7), pp.137-152. https://doi.org/10.31026/j.eng.2023.07.09

Marzouk, M.M. and El-Rasas, T.I., 2014. Analyzing Delay Causes in Egyptian Construction Projects. Journal of Advanced Research, 5(1), pp. 49–55. https://doi.org/10.1016/j.jare.2012.11.005

Maulana, V., Apriliani, D., Susila, D., Ardiansyah, R., 2024. Analysis of delays in housing construction Pt. Tata building facilities using the faul tree analysis method. Proceedings of the International Conference on Consumer Technology and Engineering Innovation (ICONTENTION 2023), Advances in Engineering Research 233, pp. 98-102. https://doi.org/10.2991/978-94-6463-406-8_18

Memon, A.H., Rahman , I.A., and Abul Hasan, M.F., 2014. Significant causes and effects of variation orders in construction projects. Research Journal of Applied Sciences, Engineering and Technology, 7(21), pp. 4494-4502. jttps://doi.org/10.19026/rjaset.7.826

Mohammed, S.R., and Jasim, A.J., 2017. Study and analysis of the delay problems in Iraqi construction projects. International Journal of Science and Research (IJSR), 6(5), pp. 2331-2336.

Mohammed, S.R., Naji, H.I. and Ali, R.H., 2019, May. Impact of the feasibility study on the construction projects. In IOP Conference Series: Materials Science and Engineering (Vol. 518, No. 2, p. 022074). IOP Publishing.

Na Ayudhyaa, B.I. and Kunishima, M., 2017. Risks of abandonment in residential projects caused by subcontractors. Procedia Computer Science, 121, pp. 232–237. https://doi.org/10.1016/j.procs.2017.11.032

Najafabadi, E.A. and Pimplikar, P.S.S., 2013. The significant Causes and effects of delays in Ghadir 2206 residential project. Journal of Mechanical and Civil Engineering, 7(4), pp. 75–81.

Naji, H.I., Mahmood, M.S., and Mohammad, H.E., 2019, May. The Impact of financial problems related to investment projects in Iraq. 2nd International Conference on Sustainable Engineering Techniques (ICSET 2019) In IOP Conference Series: Materials Science and Engineering. IOP Publishing, 518(2), pp. 1-7.

Pourrostam, T. and Ismail, A., 2012. Causes and effects of delay in Iranian construction projects. International Journal of Engineering and Technology, 4 (5), pp. 598-601. https://doi.org/10.7763/IJET.2012.V4.441

Prasad, K.V., Vasugi, V., Venkatesan, R. and Nikhil Bhat, 2019. Analysis of causes of delay in Indian construction projects and mitigation measures. Journal of Financial Management of Property and Construction. https://doi.org/10.1108/JFMPC-04-2018-0020

Rachid,Z., Toufik, B. and Mohammed, B., 2018. Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, pp. 1-11. https://doi.org/10.1080/15623599.2018.1435234

Ravisankar, K.L., Anandakumar, S.M.E., Krishnamoorthy, V.M. and Phil, M., 2014. Study on the quantification of delay factors in construction industry. International Journal of Emerging Technology and Advanced Engineering, 4(1), pp. 105–113.

Renuka, S.M., Umarani, C. and Kamal, S., 2014. A review on critical risk factors in the life cycle of construction projects. Journal for Civil Engineering Research, 4(2A), pp. 31-36.

Rezakhani, P., 2012. Classifying key risk factors in construction projects. Bulftinul institutului politrhnic din IASI Construction and Architectural, LVIII(LXII), Fasc. 2, pp. 1-13.

Sambasivan, M. and Soon, Y.W., 2007. Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25 (5), pp. 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007

Saputro, P.B. and Wiguna, I.P.A., 2020. Analysis of the factors affecting delay in housing projects in XYZ group. The 6 th international Seminar on Science and Technology (ISST) 2020, IPTEK Journal of Proceeding Series No. (6), Institute

Teknologi Nopember, Surabaya, Indonesia, pp. 348 – 353. https://doi.org/10.12962/j23546026.y2020i6.11121

Sharma, M., Trivedi, A S. and Sharma, A., 2019. Analysis of delays in building construction projects. International Journal for Research in Applied Science & Engineering Technology (IJRASET), 7 (XII), pp. 621-629.

Sheen, S., Priyan, R. and Sugumar, S., 2017. A review on risk management in residential projects. International Journal of Engineering Research & Technology (IJERT), 6 (11), pp. 295-298. https://doi.org/10.17577/IJERTV6IS110150

Sunitha, V.D., Akasah, Z.A. and Yunus, R., 2015. An overview on the issue of delay in the construction industry. Proceedings of the International Civil and Infrastructure Engineering Conference 2014 (InCIEC 2014), pp. 313-319. https://doi.org/10.1007/978-981-287-290-6_27

Sweis, G., Sweis, R., Abu Hammad, A. and Shboul, A., 2008. Delays in construction projects: the case of Jordan. International Journal of Project Management, 26(6), pp.665–674. https://doi.org/10.1016/j.ijproman.2007.09.009

Waheeb, R., 2023. Identification of delay causes in construction projects and emergency, reconstruction- Iraq as a case study. PhD thesis, Department of Civil Engineering, Norwegian University of Science and Technology Faculty of Engineering, Norwegian. https://doi.org/10.2139/ssrn.4449802

Wang, Q.S., Dulaimi, M.F. and Aguria, M.Y., 2004. Risk management framework for construction projects in developing countries. Construction Management and Economics, 22 (3), pp. 237-252. https://doi.org/10.1080/0144619032000124689

Wasim, S.S. and Khalidi, M.A., 2018. Causes of construction project failures in Pakistan. Civil and Environmental Research, 10(7), pp .38–41.

Wiguna, I.P.A. and Scott, S., 2005.Nature of the critical risk factors affecting project performance in Indonesian Building Contracts. 21st Annual ARCOM Conference, SOAS, University of London, Association of Researchers in Construction Management, 1, pp. 225-235.

Yang, J.B. and Wei, P.R., 2010. Causes of delay in the planning and design phases for construction projects. Journal of Architectural Engineering, 16(2), pp. 80-83. https://doi.org/10.1061/(ASCE)1076-0431(2010)16:2(80)

Yassin, A.T., and Al-Asadi, A., 2019. Pattern of investment projects in the investment environment. Iraq Journal of Market Research and Consumer Protection, 11(1), pp. 160-169.

Similar Articles

You may also start an advanced similarity search for this article.

Most read articles by the same author(s)